Legislación
US (United States) Code. Title 30. Chapter 14: Anthracite mine drainage and flood control
-CITE-
30 USC CHAPTER 14 - ANTHRACITE MINE DRAINAGE AND FLOOD
CONTROL 01/06/03
-EXPCITE-
TITLE 30 - MINERAL LANDS AND MINING
CHAPTER 14 - ANTHRACITE MINE DRAINAGE AND FLOOD CONTROL
-HEAD-
CHAPTER 14 - ANTHRACITE MINE DRAINAGE AND FLOOD CONTROL
-MISC1-
Sec.
571. Declaration of policy.
572. United States contributions to Pennsylvania:
authority, conditions, limitations.
(a) Contributions to be matched by Commonwealth.
(b) Amount of contributions authorized.
(c) Limitation on use of contribution.
(d) Commonwealth responsible for installation and
operation of projects.
(e) Location and operation of projects.
(f) Economic justification for abandoned coal mine
projects.
573. Statement by Commonwealth for Secretary.
574. Hearings; withholding payments.
575. Repealed.
576. Authorization of appropriations.
-End-
-CITE-
30 USC Sec. 571 01/06/03
-EXPCITE-
TITLE 30 - MINERAL LANDS AND MINING
CHAPTER 14 - ANTHRACITE MINE DRAINAGE AND FLOOD CONTROL
-HEAD-
Sec. 571. Declaration of policy
-STATUTE-
It is hereby recognized that the presence of large volumes of
water in anthracite coal formations involves serious wastage of the
fuel resources of the Nation, and constitutes a menace to health
and safety and national security. It is therefore declared to be
the policy of the Congress to provide for the control and drainage
of water in the anthracite coal formations and thereby conserve
natural resources, promote national security, prevent injuries and
loss of life, and preserve public and private property, and to seal
abandoned coal mines and to fill voids in abandoned coal mines, in
those instances where such work is in the interest of the public
health or safety.
-SOURCE-
(July 15, 1955, ch. 369, Sec. 1, 69 Stat. 352; Pub. L. 87-818, Sec.
1(1), Oct. 15, 1962, 76 Stat. 934.)
-MISC1-
AMENDMENTS
1962 - Pub. L. 87-818 declared it to be the policy of the
Congress "to seal abandoned coal mines and to fill voids in
abandoned coal mines, in those instances where such work is in the
interest of the public health or safety".
-SECREF-
SECTION REFERRED TO IN OTHER SECTIONS
This section is referred to in section 572 of this title.
-End-
-CITE-
30 USC Sec. 572 01/06/03
-EXPCITE-
TITLE 30 - MINERAL LANDS AND MINING
CHAPTER 14 - ANTHRACITE MINE DRAINAGE AND FLOOD CONTROL
-HEAD-
Sec. 572. United States contributions to Pennsylvania: authority,
conditions, limitations
-STATUTE-
The Secretary of the Interior is authorized, in order to carry
out the purposes mentioned in section 571 of this title, to make
financial contributions on the basis of programs or projects
approved by the Secretary to the Commonwealth of Pennsylvania
(hereinafter designated as the "Commonwealth") to seal abandoned
coal mines and to fill voids in abandoned coal mines, in those
instances where such work is in the interest of the public health
or safety, and for control and drainage of water which, if not so
controlled or drained, will cause the flooding of anthracite coal
formations, said contributions to be applied to the cost of
drainage works, pumping plants, and related facilities but subject,
however, to the following conditions and limitations:
(a) Contributions to be matched by Commonwealth
The amounts authorized to be contributed by the Secretary of the
Interior to the Commonwealth shall be equally matched by the
Commonwealth;
(b) Amount of contributions authorized
The total amount of contributions by the Secretary of the
Interior under the authority of this chapter shall not exceed
$8,500,000, of which $1,500,000 of the unexpended balance remaining
as of July 31, 1962, shall be reserved for the control and drainage
of water;
(c) Limitation on use of contribution
The amounts contributed by the Secretary of the Interior under
the authority of this chapter and the equally matched amounts
contributed by the Commonwealth shall not be used for operating and
maintaining projects constructed pursuant to this chapter or for
the purchase of culm, rock, or spoil banks;
(d) Commonwealth responsible for installation and operation of
projects
The Commonwealth shall have full responsibility for installing,
operating, and maintaining projects constructed pursuant to this
chapter, and shall give evidence, satisfactory to the Secretary of
the Interior, that it will enforce effective installation,
operation, and maintenance safeguards;
(e) Location and operation of projects
Projects constructed pursuant to this chapter shall be so
located, operated, and maintained as to provide the maximum
conservation of anthracite coal resources or, in those instances
where such work would be in the interest of the public health or
safety, to seal abandoned coal mines and to fill voids in abandoned
coal mines, and, where possible, to avoid creating inequities among
those mines which may be affected by the waters to be controlled
thereby; and
(f) Economic justification for abandoned coal mine projects
Projects for the sealing of abandoned coal mines or the filling
of voids in abandoned coal mines shall be determined by the
Secretary of the Interior to be economically justified. The
Secretary shall not find any project to be economically justified
unless the potential benefits are estimated by him to exceed the
estimated cost of the project.
-SOURCE-
(July 15, 1955, ch. 369, Sec. 2, 69 Stat. 353; Pub. L. 87-818, Sec.
1(2)-(7), Oct. 15, 1962, 76 Stat. 934.)
-MISC1-
AMENDMENTS
1962 - Pub. L. 87-818, Sec. 1(2), authorized the Secretary of the
Interior, in the preamble clause, to seal abandoned coal mines and
to fill voids in abandoned coal mines, in those instances where
such work is in the interest of the public health or safety.
Subsec. (b). Pub. L. 87-818, Sec. 1(3), reserved $1,500,000 of
the unexpended balance remaining as of July 31, 1962, for the
control and drainage of water.
Subsec. (c). Pub. L. 87-818, Sec. 1(4), prohibited the use of
contributions for the purchase of culm, rock, or spoil banks.
Subsec. (d). Pub. L. 87-818, Sec. 1(5), struck out "and" after
the semicolon.
Subsec. (e). Pub. L. 87-818, Sec. 1(6), prescribed that projects
be so located, operated, and maintained as to seal abandoned coal
mines and to fill voids in abandoned coal mines in those instances
where such work would be in the interest of the public health or
safety.
Subsec. (f). Pub. L. 87-818, Sec. 1(7), added subsec. (f).
-End-
-CITE-
30 USC Sec. 573 01/06/03
-EXPCITE-
TITLE 30 - MINERAL LANDS AND MINING
CHAPTER 14 - ANTHRACITE MINE DRAINAGE AND FLOOD CONTROL
-HEAD-
Sec. 573. Statement by Commonwealth for Secretary
-STATUTE-
The Commonwealth shall furnish to the Secretary of the Interior a
statement with respect to the project showing work done, the status
of the project, expenditures and amounts obligated, at such times
and in such detail as the Secretary of the Interior shall require
for the purposes of this chapter.
-SOURCE-
(July 15, 1955, ch. 369, Sec. 3, 69 Stat. 353.)
-End-
-CITE-
30 USC Sec. 574 01/06/03
-EXPCITE-
TITLE 30 - MINERAL LANDS AND MINING
CHAPTER 14 - ANTHRACITE MINE DRAINAGE AND FLOOD CONTROL
-HEAD-
Sec. 574. Hearings; withholding payments
-STATUTE-
Whenever the Secretary of the Interior, after reasonable notice
and opportunity for hearing, finds that there is a failure to
expend funds in accordance with the terms and conditions governing
the Federal contribution for such approved projects, he shall
notify the Commonwealth that further payments will not be made to
the Commonwealth from appropriations under this chapter until he is
satisfied that there will no longer be any such failure. Until he
is so satisfied the Secretary of the Interior shall withhold the
payment of any financial contributions to the Commonwealth.
-SOURCE-
(July 15, 1955, ch. 369, Sec. 4, 69 Stat. 353.)
-End-
-CITE-
30 USC Sec. 575 01/06/03
-EXPCITE-
TITLE 30 - MINERAL LANDS AND MINING
CHAPTER 14 - ANTHRACITE MINE DRAINAGE AND FLOOD CONTROL
-HEAD-
Sec. 575. Repealed. Pub. L. 105-362, title IX, Sec. 901(i)(1), Nov.
10, 1998, 112 Stat. 3290
-MISC1-
Section, acts July 15, 1955, ch. 369, Sec. 5, 69 Stat. 353; Pub.
L. 87-818, Sec. 1(8), Oct. 15, 1962, 76 Stat. 935, related to
annual reports to Congress by Secretary of the Interior on
anthracite mine drainage and flood control program.
-End-
-CITE-
30 USC Sec. 576 01/06/03
-EXPCITE-
TITLE 30 - MINERAL LANDS AND MINING
CHAPTER 14 - ANTHRACITE MINE DRAINAGE AND FLOOD CONTROL
-HEAD-
Sec. 576. Authorization of appropriations
-STATUTE-
There is hereby authorized to be appropriated such amounts as may
be necessary to carry out the provisions of this chapter.
-SOURCE-
(July 15, 1955, ch. 369, Sec. 5, formerly Sec. 6, 69 Stat. 353;
renumbered Sec. 5, Pub. L. 105-362, title IX, Sec. 901(i)(2), Nov.
10, 1998, 112 Stat. 3290.)
-MISC1-
PRIOR PROVISIONS
A prior section 5 of act July 15, 1955, ch. 369, was classified
to section 575 of this title, prior to repeal by Pub. L. 105-362,
Sec. 901(i)(1).
-End-
Descargar
Enviado por: | El remitente no desea revelar su nombre |
Idioma: | inglés |
País: | Estados Unidos |